The property was considered most energy efficient hotel in the city for many years, yet we managed to identify more savings


Customer Challenge

Unable to meet new trends in the industry with existing BMS system and need to reduce energy cost to meet competition.

The Solution

Install and commissions EPC 33 solution by LEC. Included, upgrade of essential plant, replacing traditional BMS system with next generation BEMS system of Schneider Struxuware, installation of BMS network with de-centralized system for stability and security.

Customer Benefits

Integration of mechanical and Electrical

Monitoring critical equipment and trends

Operate efficient and intelligent building asset

The Project

Investment : USD 400,687
Payback / ROI : 4 years
Guaranteed kWh saving per year : 1,091,868
Green house gas savings per year : 768 tonnes

Achieved

Energy Savings : 1,113,533 kWh/year
GHG Emissions : 778 tonnes/year